Status of the Illinois site: Response to RFC 116
An April 1971 update on the Illinois site's network connection work.
Bouknight, J., "Status of the Illinois site: Response to RFC 116", RFC 156, DOI 10.17487/RFC0156, April 1971, <https://www.rfc-editor.org/info/rfc156>.
@misc{rfc156,
series = {Request for Comments},
number = 156,
howpublished = {RFC 156},
publisher = {RFC Editor},
doi = {10.17487/RFC0156},
url = {https://www.rfc-editor.org/info/rfc156},
author = {J. Bouknight},
title = {{Status of the Illinois site: Response to RFC 116}},
pagetotal = 1,
year = 1971,
month = apr,
} RFC text
Network Working Group J. Bouknight Request for Comments: 156 26 April 1971 Category: G.5 Illinois Obsoletes: None Updates: None Status of the Illinois Site (Response to RFC 0116) As of the date of the report, 26 April, the Illinois Site has complete operational hardware connecting the PDP-11 system with the IMP. Due to much trouble with the Burroughs B6500 computer, final checkout of the operating system plus the network control program for the PDP-11 has been seriously curtailed. Current expectations are: --checkout of the NCP by the latter part of May --installation of the PDP-11 system in Paoli, PA (the operating link between Illinois and Burroughs in Paoli) so that the system will be operational during June [ This RFC was put into machine readable form for entry ] [ into the online RFC archives by Tom McGhan 7/97 ]
ISO Plain Language
On this page
§1Hardware and Software Status
As of 26 April, the Illinois site had operational hardware connecting its PDP-11 system with the IMP. This report responds to RFC 116.
Trouble with the Burroughs B6500 had seriously curtailed final checkout of the PDP-11 operating system and network control program (NCP).
The connection hardware was working. The software still needed testing, which had been delayed by trouble with the Burroughs B6500.
§2Expected Schedule
The report expected NCP checkout to finish by the latter part of May. It also expected the PDP-11 to be installed in Paoli, Pennsylvania, where it would provide the operating link between Illinois and the Burroughs system.
The report expected the system to be operational during June. These dates are expectations, not confirmed results.
The team expected to finish NCP testing by late May. It planned to install the PDP-11 in Paoli and have the system operating during June.
§3Scope of the Report
This short RFC records a site's status and expected schedule; it does not specify a protocol. The unit metadata says it updates RFC 116 and lists its status as Unknown.
This document records progress and plans at one site. Its metadata says it updates RFC 116.